Buskirk Bridge Update.
June 2, 2005, Buskirk, NY - Joe, To keep you updated on the Buskirk Covered
bridge, the bridge is now completed and open to all traffic. Here are some pictures taken on
Memorial Day weekend. No one was around to talk to, so I do not know at this time if there will
be an official opening. The repaired bridge looks just like the old Buskirk Bridge and a traditional
floor was put in instead of the laminated floor. I was sure happy to see that. I will let you know
when I find out more information.
Dick
Wilson
|
|
Buskirk Bridge, NY-42-01 photo by Dick Wilson,
May 30, 2005
|
Buskirk Bridge, NY-42-01 photo by Dick Wilson, May 30,
2005
|
|
|
Buskirk Bridge, NY-42-01 photo by Dick Wilson,
May 30, 2005
|
Buskirk Bridge, NY-42-01 photo by Dick Wilson, May 30,
2005
|
Buskirk Bridge Open April 1.
April 1, 2005, Buskirk, NY - It has been a long struggle, but the bridge is open, says
Dick Wilson, President of the New York State Covered Bridge Society.
Washington County Superintendent of Public Works
Willy Grimmke announced that the renewed span had passed inspection and will be opened to
vehicle and foot traffic April 1. However, some finishing work remains to be done.
South Cambridge and Buskirk are conveniently
connected again and may once more share emergency services.
|
|
Buskirk Bridge, NY-42-01 photo by Dick Wilson,
April, 2005
|
Buskirk Bridge, NY-42-01 photo by Dick Wilson, April,
2005
|
|
|
Buskirk Bridge, NY-42-01 photo by Dick Wilson,
March 15, 2005
|
Buskirk Bridge, NY-42-01 photo by Dick Wilson, March 15,
2005
|
More Money For Buskirk Bridge
Cambridge, NY February 24, 2005 - The Washington County Board of Supervisors
voted to amend the contract for ongoing repairs to the Buskirk Covered Bridge adding
$102,000.
The increase was said to be due to construction delays
and additional inspections. To date the cost of the reconstruction of the historic bridge spanning
the Hoosic River is $2.5 million nearly twice the original estimate of $1.3 million.
Area residents are reported frustrated with the costs
and delays. The bridge has been closed for two-and-a-half years and is not expected to open until
late May, 2005. The delays were caused by efforts to preserve the bridge rather than replace it
with a modern span. Also, instead of a projected carrying capacity of 17 tons, the renewed bridge
will be limited to 7 tons despite the replacement of 90 percent of the bridge's original fabric with
new material.
The bridge repairs were funded by Federal and state
grants meant to repair all three of the Washington County covered bridges, the Rexleigh,
Eaglrville, and the Buskirk. However the funds were exhausted on the Buskirk Bridge, it being
most in need of work
[Our thanks to Dick Wilson for forwarding the clipping from the Feb. 24 edition of The
Eagle on which, in part, this report is based -Ed.]
Return to Table of Contents
Buskirk Bridge Completion Postponed Until June 2005
CAMBRlDGE, NY - During the town of Cambndge's regular December meeting
Supervisor JoAnn Trinkle informed the board that the completion date for the Buskirk Covered
Bridge has been postponed until June of 2005.
Trinkle teamed of this information while attending a
meeting with Washington and Rensselaer county officials and project engineers at the bridge site.
She said she was told the bridge will possibly open to traffic in March 2005 with a probable, but
not guaranteed, total project completion in June.
At that meeting Trinkle asked one of the engineers
how. much of the original bridge had been preserved. He would not give Trinkle a percentage but
only pointed out some of the darker beams and said that they had come from the original bridge.
To Trinkle it appeared that most of the reconstructed bridge was new with very few parts
remaining from the original bridge.
[From the Eagle, Thursday, December 16, 2004. Clipping forwarded by Dick
Wilson -Ed.]
Return to table of contents
Buskirk Bridge Repair Progress
November 22, 2004 - Joe, I will give you the latest on the Buskirk Covered
Bridge
The pictures of the Buskirk Bridge were taken August
2004, but on a visit on October 10th, the bridge still looked like this, with work being
done on one abutment. Work was being held up as they had to get new iron rods for the Howe
Truss. The bridge is gone as you can see.
Time will tell what the new Buskirk Bridge will look
like. If I get up that way soon, I will update you on the progress.
Dick Wilson
|
|
Buskirk Bridge, NY-42-01 photo by Dick Wilson,
August, 2004
|
Buskirk Bridge, NY-42-01 photo by Dick Wilson, August,
2004
|
We visited the Buskirk Covered Bridge on July 5th and found that the long glulam beams
from Unadilla, N.Y. have been delivered. These will be used for the bottom chords. The floor has
been removed and all you can see are the cross members that were under the floor. This project is
coming along real well now.
Dick Wilson
|
|
Buskirk Bridge [NY-42-02] Photo by Dick
Wilson, July 5, 2004
|
Buskirk Bridge [NY-42-02] Photo by Dick Wilson, July 5, 2004
|
Return to Table of Contents
Buskirk Bridge is really coming along
June 23, 2004 - Buskirk Bridge is really coming along now. All false
work is in the river and the bridge is being jacked up now. You can even see a small camber in the
bridge. The boiler plate is being removed and my photo shows just how much was used on the
bottom chord. The same construction company that repaired your Poland Bridge is doing the
Buskirk Bridge. This would be a good time to see a bridge being repaired and you can get some
good shots of a Howe Truss. All these pictures were taken on June 19th, 2004.
Dick
Wilson
|
|
Buskirk Bridge [NY-42-02] Photo by Dick
Wilson, June 19, 2004
|
Buskirk Bridge [NY-42-02] Photo by Dick Wilson, June 19, 2004
|
|
|
Buskirk Bridge [NY-42-02] Photo by Dick
Wilson, June 19, 2004
|
Buskirk Bridge [NY-42-02] Photo by Dick Wilson, June 19, 2004
|
Return to Table of Contents
Buskirk Bridge Repairs underway.
April 18, 2004 - Buskirk Covered Bridge was visited on April 16th
and we found all the siding removed and the roof also removed. Abutment work is well on its way
on the Washington County side. This is a good time to see former repair work on both ends with
boiler plate and how it did not work. This old patch up work will all be gone soon.
Dick
Wilson
|
|
Buskirk Bridge [NY-42-02]
Photo by Dick Wilson, April 16, 2004
|
Buskirk Bridge [NY-42-02] Photo by Dick Wilson, April 16, 2004
|
Return to Table of Contents
Work on Buskirk Bridge Begun [WGN 32-42-02]
Buskirk, NY - Closed since a cracked beam was found in August 2002, preliminary
repairs on the Buskirk Covered Bridge have begun, with reconstruction to begin in the
spring.
The work will be done under a $1.7 million contract
awarded by the County in October. A temporary bridge to carry traffic was planned for but the
land owner adjacent to the covered bridge refused permission to establish a temporary right-of-
way.
The county wants to build a new bridge to augment
the covered bridge and has applied to add the new bridge to a federal transportation package that
will be available in 2010. A location for the new bridge has not been determined.
The covered bridge spans the Hoosic River, joining
Rensselaer and Washington counties. For commerce and emergency services, it is important that a
bridge be available at all times. The community around the bridge is served by the Buskirk Fire
Department on the Rensselaer County side. When the covered bridge is reopened it will be rated
for 12 tons. A new steel bridge will carry 25 tons, sufficient to support emergency vehicles.
[Our thanks to Dick Wilson for forwarding the news clipping on which this report is based -
Ed.]
Return to Table of Contents
Buskirk Bridge Refurbishing Plans Near
Completion
[WGN 32-42-02/58-04]
July 2, 2003 - The contract for work on the bridges will soon go out to bid, said
James Prendergast, member of the Washington County Covered Bridge Advisory
Committee.
Return to table of contents
Start Date Set for Buskirk Bridge Rehab
Buskirk, N.Y. -- Rehabilitation will begin on the Buskirk Covered Bridge in March,
2004. The work will be done by Alpine Construction of Stillwater, N.Y., the low bidder.
The construction contract, let for just under $1.8 M
was approved by the Washington County Board of Supervisors on November 21. Eighty percent
of the cost will be paid through a federal transportation improvement grant with the state
contributing 15 percent. Rensselaer and Washington counties will fund the balance.
Because the rehabilitated bridge will be required to
support fire trucks, glulam will need to be used to replace the lower chords of the bridge to attain
a load rating of 25 tons.
The Buskirk Covered Bridge was closed to traffic on
August 14, 2002 when a severe structural defect was discovered in one of the beams that
supports the bridge during a routine annual inspection of the bridge. Washington County
engineers closed the bridge until repairs could be made.
The 164-foot bridge was built in 1880 using the
Howe truss. The bridge spans the Hoosic River serving County Road 103, connecting Rensselaer
and Washington Counties.
[Thanks to John Dostal for forwarding the news clipping that was the basis for this article -
Ed.]
Return to table of contents
New York's Buskirk Bridge Closed
|
The Buskirk Bridge photo by Dick Wilson
August 17, 2002.
|
BUSKIRK, N.Y. The Buskirk Covered Bridge was closed to traffic Wednesday
afternoon, August 14 due to a "substantial new crack in one of the crossbeams," according to the
Post-Star of Glens Falls, N.Y. The Bennington Banner of Bennington Vermont
declares the closing was due to "a severe structural defect . . . . in one of the beams that holds up
the bridge."
According to the news items, the problem was found
when the bridge was undergoing one of its twice annual inspections. Washington County
engineers made the decision to close the bridge.
The bridge connects Washington and Rensselaer
Counties over the Hoosic River, the only crossing for five miles in each direction. The detour is a
cause for concern for the Buskirk Fire Department and other emergency services. An estimated
700 cars each day will need to use the Johnson or the Eagle Bridge until the Buskirk span is
returned to service.
Renovations at an estimated cost of $900,000, to be
shared by the two counties, had been scheduled for 2003. Interim repairs are being planned.
The Buskirk Bridge (World Guide Numbers 32-42-02
and 32-58-04) is described in the newspaper articles as a 164-foot single span constructed in 1857
using the Howe Truss. The World Guide To Covered Bridges published by the National
Society for the Preservation of Covered Bridges lists the bridge as having been built in 1880
Many thanks to Dick Wilson, President of the New
York State Covered Bridge Society, for forwarding the referenced newspaper clippings.
|